Roadworks Ahead For the Ivers 25th June - 16th August

Please note that dates are indicative and The Ivers Parish Council has no control over the scheduling of roadworks

 

During the period 25 Feb – 9 Aug, resurfacing work is scheduled to take place in the following locations:

  • Pinewood Road – entire length (currently listed as during the period 6 – 25 Jun).
  • Glaisyer Way – entire length.
  • High Street – junction with Cecil Road to junction with Langley Park Road
  • Langley Park Road – junction with High Street to the canal bridge.

 

In each case, the road will be subject to closure and diversions will be in place and so delays and parking restrictions are inevitable.

23 Apr – 16 Aug  Pinewood Road – 5-points roundabout to Pinewood Studios.  Construction of cycleway.  Lane closure – Delays possible.

14 – 29 Jun         Wood Lane – entire length.  Water meter installation.  Give and take – Delays unlikely.

20 – 26 Jun         Grange Way – by entrance to school/car park.  Repairs to footway.  Give and take – Delays unlikely.

20 Jun – 1 Jul      A412 Church Road – outside St Margaret’s Church.  Gas repairs.  No carriageway incursion – Delays unlikely.

21 – 25 Jun         Pinewood Road – outside Maythorne Cottage.  Water main installation.  No carriageway incursion – Delays unlikely.

24 - 26 Jun          Post Meadow – outside No. 20.  Telecoms works.  No carriageway incursion – Delays unlikely.

26 – 27 Jun         Pinewood Green – outside No. 92.  Telecoms works.  No carriageway incursion – Delays unlikely.

2 – 8 Jul              Thorney Mill Road – various points.  Telecoms works.  Two-way traffic signals – Delays likely.

7 Jul                     B470 High Street – outside No. 56.  Water main works.  Two-way traffic signals – Delays likely.

The Ivers Parish Council logo

Contact Us

Iver Parish Council
45B High Street,
Iver,
Buckinghamshire,
SL0 9ND

01753 655331
This email address is being protected from spambots. You need JavaScript enabled to view it.

Twitter Feed