The following major resurfacing works are planned. Dates indicate only the window during which the work is expected to take place and not the duration of the works.
 
9 Apr – 7 Aug
Swan Road. Resurfacing. Road closure
13 Apr – 2 Oct
St David’s Close - Entire length. Plane and patch. Road closure.
12 - 13 Jul
Denham Road – Entire length. Plane and patch. Night-time road closure.
6 – 14 Jul
A412 Church Road – Entire length. Plane and patch. Road closure.
10 – 13 Jul
Chequers Orchard - Entire length. Plane and patch. Daytime road closure between 07:00-19:00.
17 – 25 Jul
Iver Lane – Entire length. Plane and patch. Road closure.
w/c 20 Jul
Hardings Row – Entire length. Plane and patch. Road closure.
w/c 20 Jul
Coopers Row - Entire length. Plane and patch. Road closure.
w/c 20 Jul Potters Cross - Entire length. Plane and patch. Road closure.
Exact timing will be posted two weeks before work is due to commence.
29 Jun – 3 Aug
Chequers Orchard – entire length. Gas main replacement. Some carriageway incursion – Delays unlikely.
10 -15 Jul
Glaisyer Way – outside No. 31. Water main repairs. Some carriageway incursion – Delays unlikely.
13 Jul – 14 Aug
Iverdale Close – outside Nos 4-18 and 20-28. Gas main replacement. Some carriageway incursion – Delays unlikely.

Video

Roadworks Ahead For The Ivers  - Up to and including October 2nd 2020
The Ivers Parish Council logo

Contact Us

Iver Parish Council
45B High Street,
Iver,
Buckinghamshire,
SL0 9ND

01753 655331
This email address is being protected from spambots. You need JavaScript enabled to view it.

Twitter Feed